Project Drogheda | Helgen CTO | 2026-09-10 | Draft — evaluation procedure |
Backup-power evaluation: the procedure
It is not a lot of things to do. It is three measurements and a decision. Everything else in the last three notes is contingent on them — most of that list deletes itself once D3, P1 and P2 come back. Do not start firmware before Gate G1.
Critical path: D3 (requirement) → P1 (sleep floor) → P2 (modem) → F1 (firmware) → S1 (server) → decide the cell last. ≈ 3 weeks of elapsed time, ~7 person-days of work.
Phase D — desk, no hardware. 1 day. Kills most of the list.
| # | Task | Owner | Output |
|---|---|---|---|
| D1 | Fleet tbat/tntc histogram from htracker: hourly distribution per unit over 30 d; % of day above 42 °C; longest continuous window below 40 °C; correlate cflt and charge events with those windows |
backend | one chart + two numbers |
| D2 | Ask Telcel: is PSM / eDRX available on our APN and plan? What TAU / Active Timer will the network grant? | Leo | yes/no + granted timers |
| D3 | 🔴 Pin the requirement. From ICAVE ops / the contract, not from us: how long must a unit keep reporting on battery, and what must it report? | Leo | a number in hours, and a message spec |
Gate G0 — do not proceed without D3. Every number downstream is sized by it. If the answer is "report the outage and survive until someone attends, ~24 h", the whole problem is already solved by the firmware and the cell question closes. If it is "7 days of live tracking", that is a different product and needs a different pack.
D1 query sketch
SELECT cell_id, date_trunc('hour', ts) AS h,
avg(tbat) AS tbat_avg, max(tbat) AS tbat_max,
sum((tbat > 42)::int)::float / count(*) AS frac_above_42
FROM phlg WHERE ts > now() - interval '30 days' AND tbat > -100
GROUP BY 1,2 ORDER BY 1,2;
Then: per unit, the longest run of consecutive hours with tbat_max < 40.
Success bar is not "always cool" — it is "≥ 15 min below 40 °C per day" (see the
duty-cycle brief §3). That is a much easier bar and may already be met.
Phase P — bench. The measurement that decides everything. 2–3 days.
Rig
One v5.5 board, bench PSU at 3.7 V into P4 (pack position), current measured
at BAT+ — that is what the pack actually delivers, and it captures the LTC4040
boost's light-load efficiency, which is one of our real unknowns. Measure the 5 V rail in
parallel so you get both numbers and can derive the boost efficiency.
⚠ A bench DMM will not do this. You need µA-to-A dynamic range on one trace: a Nordic PPK2 (~US$110) or Joulescope/Otii. Buy it — it pays for itself in this test alone, and every low-power decision after this depends on trusting the number.
P1 — the subtraction ladder 🔴
Measure, then remove one load, measure again. The deltas are the deliverable — they tell you which fixes are worth writing and which are noise.
| Step | State | Expect |
|---|---|---|
| a | Full RUNNING, stack up, fan off |
~2.5 W baseline |
| b | PWR_CTRL low (RTK stack off) |
|
| c | BYP_CTRL low (K1 released) |
−150 mW — confirms the K1 reversal |
| d | U12 disabled + W5500 held in reset |
−400 mW? |
| e | All LEDs off (incl. gauge PB12–15) |
−50…150 mW |
| f | MAX3232 / SP3485 / SC16IS752 in shutdown |
−5…15 mW |
| g | MCU in STOP + LSE RTC (not loop()) |
−150 mW |
| h | U17 lifted, /3V3 fed from bench supply through the meter |
isolates the AMS1117's own Iq — the number I most expect to be ugly |
Gate G1: is the achievable floor under 50 mW? Yes → proceed to firmware. No → find out what is holding it up before writing any. If step (h) is 25–55 mW as expected, the LDO swap is a one-part change worth doing first.
P2 — modem energy and the burst
- Real Telcel SIM. If D2 said yes:
AT+CPSMS=1,,,"<TAU>","<Active>". Measure modem sleep current in PSM, and energy per wake→TX→sleep cycle in joules. - If D2 said no: measure energy per full attach cycle the same way.
- 🔴 The burst test. With a real pack at low SoC and the pack at 45 °C,
trigger an LTE attach and watch
MAIN5Von a scope. DoesPFI(4.60 V) trip? This is the most likely way the design fails in the field and it is cheap to check now.
Gate G2: PSM or power-cycle, and the interval locked. Feed the measured joules back into the runtime table.
Phase F — firmware. 3–4 days, once G1 and G2 pass.
BACKUP_SLEEPas a real state behind a compile flag (ENABLE_BACKUP_DUTYCYCLE), per the state machine in the duty-cycle brief §8. Today'sSLEEPstays as the brownout failsafe.- Exercise it first in the
hostsimharness already in the repo — state transitions, adaptive cadence,BAT_CRITICALfinal message — before it touches silicon. - F1 acceptance, on the bench: real pack, real SIM, 72 h continuous with the meter logging. Deliverable = measured Wh/day and extrapolated runtime.
- Gate G3: measured Wh/day within 30 % of the model. If it is not, the model is wrong and everything downstream needs re-deciding — do not paper over it.
Phase S — server-side synthesis. Your idea, and it is a good one. 1–2 days.
Holding the position server-side decouples what the customer sees from what the radio does.
The device sends a heartbeat every 30–60 min; retranslator.py keeps feeding Wialon at
1 Hz from the last known fix. That is the right split.
But three rules, and they are not optional:
- Mark it. Synthesized points carry an explicit source flag and render differently in the UI. We are generating data that did not come from a sensor; anyone reading the track must be able to see that. Do not let a synthesized point be indistinguishable from a real one.
- 🔴 Hard stop on a missed heartbeat. The moment a heartbeat is late by more than one interval, stop synthesizing and switch the unit to "last seen at X, T ago — unknown". Synthesizing past the heartbeat window turns a dead unit into a healthy-looking one on the operator's screen. That is strictly worse than reporting nothing, and it is exactly the failure this feature would be blamed for.
- Movement breaks the illusion instantly. The
U26accelerometer wake exists for this: if the machine moves during an outage, the unit wakes and sends a real fix, and the server drops out of synthesis on the spot. Without motion-wake, a towed machine keeps reporting from the yard — with a port customer, that is a liability, not a bug.
S1 test: on the bench, cut vehicle power → verify Wialon shows a continuous 1 Hz track flagged as battery-mode → cut the unit entirely → verify the track stops and the unit goes "unknown" within one heartbeat interval, not later. Also check whether ICAVE's contract or Wialon billing counts records — synthesized ones may not be acceptable to count.
Phase C — the cell decision, last
Only now, with measured Wh/day (F1) and the real temperature histogram (D1):
- Daily energy < ~2 Wh and D1 shows ≥ 15 min/day below 40 °C → keep the current cell.
No LFP, no
RNTBchange, no new case. Consider shrinking the pack instead. - Otherwise → high-temp LFP +
RNTB→ 5.6 k + B3380 NTC +JP2re-strap, per the battery note. Order sample cells at D1 time so they are on the shelf if needed — that is the only long-lead item, and sampling two cells costs nothing.
Phase V — field pilot. 30 days.
Two units at ICAVE on the new firmware, rest of the fleet as control. Track: actual outage
events, hours survived, vbat trajectory, charge-window utilisation, and any operator
complaint about the synthesized track. Ship to the fleet only after 30 clean days.
What this is not
Not a v6 respin. Nothing above requires new hardware except a possible one-part LDO swap and, if Phase C says so, a cell and one resistor. The 30-unit build is not blocked by any of it — but D3 should be answered before that build ships, because it may change what pack goes in the box.