Drogheda Hackathon — Run-of-Show, Backlog & Gantt
A weekend push to stabilize the fleet and de-risk the production build. Dates
below assume a Fri-evening → Sun weekend; adjust to your chosen weekend.
Goal: leave Monday with the backend fixed, firmware v2 bench-validated, the 4
pulled units triaged, the thermal number measured, and the PCB schematic started.
1. Objectives (definition of success)
- Backend stops killing healthy units — anti-jump hotfix + cell_id identity
deployed; 500-unit slow-upstream load test passes; secrets rotated.
- Firmware v2 bench-validated — recovery/backoff/LIMP/thermal verified on a
real Blackpill + simpleRTK2B; flash candidate signed off.
- The 4 pulled units classified — hardware-dead vs backend-victim; RCA updated.
- Thermal quantified — a real cabinet-interior temperature from a soak test;
battery + thermal-path decisions made.
- Production kicked off — watchdog schematic → first PCB schematic draft;
BOM + SRS signed off; Notion board live.
2. Tracks & suggested owners
| Track |
Focus |
Suggested owner |
| A — Backend |
anti-jump hotfix, cell_id identity, load test, deploy, secrets |
Gibran + Leo |
| B — Firmware |
bench-test v2, recovery/thermal validation, flash candidate |
Leo |
| C — Hardware/Thermal |
soak test, battery & thermal-path decisions, conduction mock-up, fuse check |
Daniel |
| D — Diagnostics |
triage 4 pulled units (remote-hands/shipped), classify, RCA update |
Gibran |
| E — PCB/Docs |
schematic from watchdog spec, BOM/SRS sign-off |
Leo + Daniel |
| F — PM/Integrations |
Notion board, Drive sync, client comms, run-of-show |
Adriana |
3. Run-of-show
| When |
Block |
Output |
| Fri PM |
Kickoff; assign tracks; backend historical triage (htracker-online vs Wialon-offline); bench setup |
which "dead" units are backend victims; benches ready |
| Sat AM |
A: anti-jump hotfix + cell_id · B: v2 bench bring-up · C: start thermocouple soak · D: unit power-on + current-draw |
hotfix in test; v2 booting; soak logging; first unit classified |
| Sat PM |
A: 500-unit slow-upstream load test · B: forced-outage recovery test · C: battery/thermal-path decision · E: PCB schematic start |
load test result; recovery proven; material decisions; schematic skeleton |
| Sun AM |
A: deploy fixed retranslator + rotate secrets · D: finish triage + RCA update · E: BOM/SRS sign-off |
backend live; 4 units classified; docs frozen |
| Sun PM |
Integrate; demo; definition-of-done checklist; retro; next-week plan |
go/no-go; backlog for week +1 |
4. Gantt
gantt
dateFormat YYYY-MM-DD
title Drogheda Hackathon (adjust dates to your weekend)
axisFormat %a
section A Backend
Historical triage :a1, 2026-06-19, 1d
Anti-jump hotfix + cell_id :a2, 2026-06-20, 1d
500-unit load test :a3, after a2, 1d
Deploy + rotate secrets :a4, 2026-06-21, 1d
section B Firmware
v2 bench bring-up :b1, 2026-06-20, 1d
Recovery/thermal validation :b2, after b1, 1d
Flash candidate sign-off :b3, 2026-06-21, 1d
section C Hardware/Thermal
Thermocouple soak :c1, 2026-06-20, 2d
Battery + thermal decision :c2, 2026-06-20, 1d
Conduction mock-up :c3, 2026-06-21, 1d
section D Diagnostics
Power-on + current draw :d1, 2026-06-20, 1d
Classify + RCA update :d2, 2026-06-21, 1d
section E PCB/Docs
PCB schematic draft :e1, 2026-06-20, 2d
BOM + SRS sign-off :e2, 2026-06-21, 1d
section F PM
Notion board + Drive sync :f1, 2026-06-19, 1d
Demo + retro :f2, 2026-06-21, 1d
5. Prioritized backlog (pull into Notion)
| P |
Item |
Track |
DoD |
| P0 |
Anti-jump hotfix (time-aware + self-heal + clear on TTL) |
A |
healthy unit can't be permanently dropped; unit test |
| P0 |
cell_id identity (drop source-IP keying) |
A |
CGNAT-safe pairing; verified with 2 sims behind 1 IP |
| P0 |
v2 forced-outage recovery test |
B |
recovers via power-cycle within backoff, no loop |
| P0 |
Thermocouple soak (measure cabinet interior) |
C |
a real °C number over a sunny shift |
| P0 |
Classify the 4 pulled units |
D |
each tagged dead/backend-victim; RCA updated |
| P1 |
500-unit slow-upstream load test |
A |
no unit dropped; metrics captured |
| P1 |
Confirm ASA case survives soak (expected OK) |
C |
sample part survives soak |
| P1 |
Battery decision (drop/LiFePO4/supercap) |
C |
FR-7 closed |
| P1 |
Rotate MSSQL secret + purge from git |
A |
secret out of repo + history |
| P1 |
PCB schematic from watchdog spec |
E |
reviewable schematic |
| P2 |
Front-panel SIM / MFF2 |
E |
maintainability path chosen |
| P2 |
Verify cabinet blade fuse |
C |
rated vs worst-case + inrush |
6. Logistics / pre-reqs
- Benches: 24 V supply with current limit + meter, Blackpill + simpleRTK2B +
4G master + antennas with sky view, USB-serial laptop.
- The 4 pulled units in QRO (ship) or remote-hands in VER —
06-Testing-Validation/remote-diagnostic-protocol.
- htracker repo + a staging caster/Wialon endpoint for the load test.
- Notion workspace + Drive access for the team.